The Intent To Lien Florida form serves as a formal notification to property owners regarding an impending claim of lien due to non-payment for labor, services, or materials provided for property improvements. This notice is mandated by Florida law and must be issued at least 45 days before the lien is recorded. Failure to respond within 30 days can result in legal actions, including foreclosure proceedings.

Access This Intent To Lien Florida Now

The Intent to Lien Florida form serves as a crucial tool for contractors, suppliers, and service providers seeking to protect their rights in the event of non-payment for services rendered. This formal notice is typically sent to property owners and, when applicable, to general contractors, outlining the intent to file a lien against a property due to unpaid debts. The form requires specific details, including the names and addresses of the involved parties, a description of the property in question, and the amount owed for the work completed. Importantly, it adheres to Florida Statutes §713.06, which mandates that this notice be provided at least 45 days before any lien is recorded. By issuing this notice, the sender informs the property owner of the outstanding payment and the potential consequences of inaction, such as foreclosure proceedings and additional costs related to legal fees. The form also emphasizes the importance of prompt communication, encouraging the property owner to resolve the matter amicably to avoid escalation. This proactive approach not only safeguards the interests of those who have provided labor or materials but also serves to foster transparency and communication between all parties involved in a construction project.

Dos and Don'ts

When filling out the Intent To Lien Florida form, there are important steps to follow. Here’s a list of things to do and avoid:

  • Do include the correct date at the top of the form.
  • Do clearly state the property owner's full legal name and mailing address.
  • Do provide the general contractor's name and address if applicable.
  • Do accurately describe the property, including both the street address and legal description.
  • Do specify the amount owed for the work performed.
  • Don't forget to sign the document before sending it.
  • Don't leave any sections blank; ensure all information is complete.
  • Don't use vague language; be clear and direct in your communication.
  • Don't ignore the timeline; send the notice at least 45 days before filing a lien.
  • Don't overlook the certificate of service; ensure it is filled out correctly.

Key takeaways

Filling out and using the Intent to Lien Florida form is an important step for contractors and suppliers who have not received payment for their services. Here are some key takeaways to keep in mind:

  • Timeliness is Crucial: The notice must be sent at least 45 days before filing a Claim of Lien. This timeline is essential to comply with Florida law.
  • Clear Communication: Ensure that the property owner's full legal name and mailing address are accurately filled out. This helps avoid any disputes regarding the validity of the notice.
  • Specificity Matters: Clearly describe the property and the nature of the work performed. This information is vital for establishing the basis of your claim.
  • Payment Details: Include the exact amount owed. This transparency encourages the property owner to respond and settle the debt promptly.
  • Consequences of Inaction: Highlight that failure to respond within 30 days could lead to a lien being recorded. This serves as a strong reminder of the potential legal ramifications for the property owner.

By following these guidelines, individuals can navigate the process more effectively and protect their rights in the event of non-payment.

Find Common Documents

Example - Intent To Lien Florida Form

NOTICE OF INTENT TO FILE A LIEN

Date: ______________

To:

Property Owner's Full Legal Name(s):

____________________________________________________________

Property Owner's Full Mailing Address:

____________________________________________________________

Cc:

General Contractor's Full Legal Name(s), if applicable:

____________________________________________________________

General Contractor's Full Mailing Address:

____________________________________________________________

Re: _________________________________________________________

Property Description:

Street Address: _______________________________________________

Legal Description: _____________________________________________

____________________________________________________________

Dear ___________________,

This Notice is being sent to inform you that ___________________________, having furnished

labor, professional services, and/or materials for improvements to the property described above, intends to record a Claim of Lien against the property for non-payment.

Pursuant to Florida Statutes §713.06(2)(a), this Notice of Intent to File a Lien is being served not less than 45 days prior to recording a Claim of Lien against the property. This notice apprises you that we have not received payment in the amount of _____________________

for work performed on the project.

As per Florida Statutes §713.06(2)(b), failure to make payment in full or provide a satisfactory response within 30 days may result in the recording of a lien on your property. If the lien is recorded, your property could be subject to foreclosure proceedings, and you could be responsible for attorney fees, court costs, and other expenses.

No waivers or releases of lien have been received that would affect the validity of this lien claim.

We would prefer to avoid this action and request your immediate attention to this matter. Please contact us at your earliest convenience to arrange payment and avoid further action.

Thank you for your prompt attention to this matter.

Sincerely,

_________________________ [Your Name]

_________________________ [Your Title]

_________________________ [Your Phone Number]

_________________________ [Your Email Address]

CERTIFICATE OF SERVICE

I certify that a true and correct copy of the Notice of Intent to File a Lien was served on

______________ to ____________________________ at

__________________________________________ by:

Certified Mail, Return Receipt Requested

Registered Mail

Hand Delivery

Delivery by a Process Server

Publication

____________________________

____________________________

Name

Signature

Misconceptions

Here are five common misconceptions about the Intent to Lien Florida form:

  • It guarantees a lien will be filed. Many believe that submitting this notice automatically leads to a lien being placed on the property. In reality, it serves as a warning that a lien may be filed if payment is not made.
  • It can be sent at any time. Some think they can send this notice whenever they wish. However, Florida law requires that it be sent at least 45 days before filing a lien.
  • Payment must be made immediately after receiving the notice. Recipients often feel pressured to pay right away. They actually have 30 days to respond or make payment before a lien can be recorded.
  • It is only for contractors. Many assume that only general contractors can use this form. In fact, subcontractors and suppliers can also file this notice if they have not been paid.
  • It is not necessary if a contract exists. Some believe that having a contract negates the need for this notice. However, even with a contract, this notice is essential for protecting the right to file a lien.

Similar forms

  • Notice of Lien: This document formally establishes a claim against a property due to unpaid debts. Like the Intent to Lien form, it serves to notify the property owner of the outstanding balance and the potential consequences of non-payment.
  • Notice of Non-Payment: This notice informs the property owner that payment has not been received for services rendered. Similar to the Intent to Lien, it highlights the urgency of resolving the matter before further legal action is taken.
  • Claim of Lien: This document is filed to secure a creditor's interest in a property. It follows the Intent to Lien and requires the same information, such as the property description and the amount owed.
  • Mechanic's Lien: This is a specific type of lien that contractors and suppliers can file when they are not paid for work done on a property. It shares the same purpose of protecting the claimant's right to payment.
  • Demand Letter: A demand letter requests payment for services or goods provided. Like the Intent to Lien, it serves as a formal communication that may precede legal action if the issue is not resolved.
  • Notice of Default: This document is sent to notify a borrower that they are in default on a loan. It parallels the Intent to Lien by alerting the recipient to the consequences of non-compliance.
  • Notice of Foreclosure: This notice informs property owners that foreclosure proceedings may begin due to unpaid debts. It is similar in that it warns of severe consequences if payment is not made.
  • Contractor's Affidavit: This document verifies that a contractor has completed work and has not been paid. It relates to the Intent to Lien by establishing the basis for a lien claim.
  • Release of Lien: This document is used to remove a lien once payment has been made. It is connected to the Intent to Lien as it signifies the resolution of the debt that initiated the lien.
  • Preliminary Notice: This notice informs property owners that a contractor or supplier has begun work on their property. Like the Intent to Lien, it serves to establish the claimant’s right to file a lien if payment is not received.